Donner Summit Public Utility District
Reason for Investigation
The Eastern portion of Nevada County has seen significant growth in the last decade. Some
public services are provided by special districts, the oversight of which is a responsibility of
the Nevada County Grand Jury (Jury). Pursuant to the California Penal Code, Section 933.5,
the Jury, noting the proposed development of the Royal Gorge Area, decided to examine the
problems and challenges such development, and additional build-out already permitted,
would have on the Donner Summit Public Utility District (DSPUD).
Background
In 1948, the State of California authorized the formation of the DSPUD to initially provide
drinking water and wastewater treatment to its property owners. Twenty-six voters approved
and three opposed the establishment of the district.
The DSPUD commenced fire protection for the area in 1973. The DSPUD ceased to provide
fire protections services when its staff, equipment and other resources were transferred to the
Truckee Fire Protection District (TFPD) in July, 2006. Administrative and treatment
facilities are located on 5.75 acres of U.S. Forest Service (USFS) land under a 20 year special
use permit which expired on 12/21/07. In April 2008, the District started discussions with the
USFS for a renewal, which could be completed in the next few months.
The DSPUD covers approximately 13 square miles in Nevada and Placer Counties; provides
drinking water to 279 customers, wastewater collection and treatment to 264 residential and
commercial customers in the communities of Norden and Soda Springs; as well as Sugar
Bowl, Boreal, Donner Ski Ranch, and Soda Springs Ski Areas. [Sewer connections are
measured in Equivalent Dwelling Units (EDU’s). DSPUD bills 540 commercial and 225
residential EDU’s, for a total of 765 EDU’s.]
An agreement with the DSPUD provides Sierra Lakes County Water District (SLCWD) 44%
of the capacity of the wastewater treatment plant to serve the Serene Lakes Community in
Placer County and 3000 acres in Placer County. SLCWD bills 805 customers for sewer
service.
The District is negotiating an agreement with the Big Bend Mutual Water Company, which
serves a Homeowners Association containing 32 cabins, to provide management and
administration of Big Bend’s water service.
The District is governed by a five member elected Board of Directors. The District has 83
voting constituents, 71 residing in Nevada County and 12 in Placer County. It holds
regular monthly dinner meetings. There is a paid staff of 6 full-time and 2 part-time people,
comprised of the General Manager, two administrative staff, and five plant and field
personnel. The 2007-8 budget estimates revenues of $1,625,285 and expenses of $1,592,936.
It is the Jury’s understanding that some years ago DSPUD and SLCWD had discussions
about merging the two districts. These discussions were terminated after several meetings of
the parties.
A dispute arose between DSPUD and TFPD regarding which agency should receive funds
for services provided to Nevada County Service Area 31 and other Nevada and Placer
County areas outside the DSPUD during the fiscal years 2004-5 and 2005-6. The Board filed
a breach of contract lawsuit in 2007 to require the disputed funds be returned to the DSPUD.
This litigation has recently been settled.
Some wastewater discharge violations are inherent in wastewater treatment operations.
However, during the period 2001-2006, DSPUD experienced 76 discharge violations, for
which the California Regional Water Quality Control Board (RWCB) imposed fines totaling
$216,000. The RWCB later waived the fines in consideration of DSPUD applying an equal
amount toward the recently completed upgrade of its wastewater treatment facilities.
The State of California has assigned "Beneficial Uses,” to the South Yuba River, which
includes municipal and domestic drinking water supply, agriculture uses, water recreation,
and wildlife habitat. Disposal of wastewater in the South Yuba River by DSPUD is a use that
is not prohibited; however, such use cannot be satisfied to the "detriment of beneficial uses.”
In 2007, Royal Gorge LLC announced plans to redevelop approximately 400 of the 1300
acres of the Royal Gorge Cross Country Ski Area, situated in Placer County. The proposed
development envisions 950 residences and other resort facilities. Royal Gorge LLC has held
preliminary discussions with DSPUD regarding expansion of the wastewater treatment
facility to service the proposed development.
Method of Investigation
The Jury conducted interviews with the President, and one other member of the Board of
Directors of the DSPUD (Board), the District’s General Manager, the District’s Plant
Operator, the President of the Board of Sierra Lakes County Water District and the General
Manager of the Sugar Bowl Ski Resort, as well as reviewing DSPUD financial, and business
records. Members of the Jury attended a Board meeting and reviewed Local Agency
Formation Commission (LAFCO) records regarding DSPUD. The Jury reviewed financial
and organizational records of other public agencies in the area that provide services
comparable to the DSPUD including the Tahoe-Truckee Sanitary Agency (T-TSA), the
Truckee Donner Public Utility District, the Tahoe City Public Utility District, and the Town
of Truckee.
Findings
1. The President of the Board receives $300, the Vice-President receives $260 and the
Directors receive $225 per regular monthly meeting. In addition, each director
receives $100 for any other meetings. They are paid whether they attend or are
excused. The monthly meetings include complimentary dinner for everyone present.
The current budget includes direct Board expenses of $16,820. By comparison, the
Truckee-Tahoe Sanitary Agency, operating a larger wastewater treatment plant, and
whose budget is 7.5 times that of DSPUD, includes $12,000 in its current budget for
Board of Directors’ fees and expenses.
2. Other than the licensed operating personnel, there is no engineering expertise on site
to evaluate the information received from retained outside consultants. The Board
members, three of whom, are in their first term, and the General Manager rely on
these consultants for technical knowledge and expertise at an annual cost of $247,000
(Includes Chief Plant Operator for part of the year).
3. A comparison of salaries (Attachment A) shows that the salaries of the General
Manager and the Chief Plant Operator are higher than comparable positions at T-
TSA. The T-TSA has a ’07-08 Operating Budget 7.5 times larger than DSPUD, and
61 staff positions compared with six full-time and two part-time employees at
DSPUD.
4. The District is spending $30,500 to insure property valued at $11,867,000. By
comparison, the T-TSA is spending $30,000 to insure property valued at $68,000,000.
5. The District does not have reserve funds.
6. Failure to have an operating website makes it difficult to provide stakeholders with
relevant information.
7. The minutes of the Board meetings are inadequate to provide a clear understanding of
Board activities.
8. The minutes of the Board meetings indicate that with the exception of invited guests -
attorneys, engineers, potential new board members, etc - almost no stakeholders
attend Board meetings.
9. The dispute with the TFPD was a result of DSPUD staff failure to execute the
contracts with Nevada County for two years to provide fire services to County
Service Area 31 and other Nevada and Placer County areas outside the DSPUD. It
involved approximately $63,000 claimed by DSPUD and the TFPD cross-complaint
for $164,462 in damages. The settlement provided that DSPUD receive $25,000 to be
spent to upgrade of the water distribution system and $5000 to upgrade the fire station
to meet code. TFPD will spend $33,000 to upgrade the fire equipment serving the
Donner Summit area.
10. Under the agreement between the DSPUD and SLCWD, DSPUD is entitled to 56%
of the capacity of the wastewater treatment plant capacity and SLCWD is entitled to
44 %. DSPUD has 83 registered voters from which to draw Board members. SLCWD
has no representation on the DSPUD Board.
11. For ten months of the year, DSPUD discharges wastewater to the South Yuba River
in the amount of 0.52 million gallons per day with the capacity to be expanded to 0.80
million gallons per day by 2010. In dry or cold years, the stream is low, and high
wastewater flows can be discharged into low stream flows.
Conclusions
1. While the T-TSA is much larger than the DSPUD, its operation of a wastewater
treatment plant makes it the most logical agency in the area to compare with the
DSPUD.
2. While it is necessary to attract citizens to participate in the governing process, the
high fee schedule for DSPUD Directors, paying them even if they do not attend a
meeting, and serving dinner at regular meetings, sends the constituents and the public
the wrong message.
3. Salaries paid by DSPUD to senior level employees seem excessive when compared
with T-TSA (see Attachment A).
4. The DSPUD property insurance cost is considerably higher than T-TSA given that the
insured property value is one-sixth that of T-TSA
5. Communication with the stakeholders is not being given sufficient priority by the
Board and staff.
6. The engineering, technology, capital investment, and personnel requirements of the
DSPUD plant will require significant upgrade to ensure proper disposal of increased
treated wastewater.
7. The Board appears to be relying largely on staff and counsel and demonstrates little
oversight, questioning and judgment.
8. The failure of the General Manager to execute the contracts with the County for fire
services and the delay in negotiating a special use permit with the USFS displayed
inadequate oversight and direction on the part of the Board.
9. The practice of DSPUD of discharging large quantities of wastewater into the low
flowing South Yuba River poses a threat to the beneficial uses of the river.
Recommendations
1. The District should embark on an extensive training program to equip the Board and
Staff with the knowledge and skills to manage the District’s future needs.
2. The District should give high priority to developing and executing a communications
strategy that will open the window for all stakeholders and interested parties. They
should complete the upgrade of the web site; expand the content, include on the web
site the Board Meeting Minutes, and publish a regular newsletter.
3. The District should develop a policy for establishment of reserve funds and create
such funds.
4. The District should investigate the extent of new technology that is or may become
available to discharge wastewater - for example, year round subsurface disposal of
wastewater.
5. The DSPUD and its related stakeholders should carefully and completely explore all
potential impacts on current users of the system and others affected before entering
into any agreements with Royal Gorge LLC or any other future development.
6. Nevada and Placer County LAFCOs, together with the DSPUD and SLCWD, should
explore the feasibility of a merger of the two districts. Boards of both districts should
seek alternate means to provide representation to the large number of users in the
SLCWD who have virtually no voice in the affairs of the District.
7. The Board should exercise greater supervision over the General Manger. This
supervision should include measurable performance indicators linked to his major
duties and to the District’s objectives.
Required Response
Donner Summit Public Utility District Board of Directors: October 6, 2008
Attachments
Attachment A DSPUD – Selected Comparisons, dated 11.13.07 revised 4/13/2008
Donner Summit PUD - Selected Comparisons
|
OPERATING BUDGET ’07- 08 |
Expenses |
Employees |
|
|
|
|
|
Donner Summit PUD |
$ 1,592,876 |
8 |
|
Tahoe-Truckee Sanitary Agency (T-TSA) |
11,951,855 |
61 (6 open) |
|
Tahoe Donner PUD |
31,000,000 |
67 |
|
GENERAL MANAGER SALARIES ’06- 07 |
|
|
|
|
|
Donner Summit PUD |
$153,142* |
|
T-TSA |
149,965 |
|
Truckee Donner PUD |
147,430 -179,192 |
|
Tahoe City PUD |
137,786 |
|
Truckee Town Mgr. |
126,203 |
*Only benefit is Long Term Disability Insurance
|
SALARY COMPARISON ’07- 08 |
|
|
|
|
|
|
|
|
Donner Summit PUD |
T-TSA |
|
|
|
|
|
General Mgr |
$158,133 |
$ 149,965 |
|
Chief Plant Operator |
105,000 |
88,608 |
|
Operations Supt. |
- |
98,352 |
|
Field Services Supvr. |
63,139 |
98,352 |
|
Operator II |
52,000 |
61,176 |
|
Operator I |
41,899 |
54,300 |
|
BOARD MEMBER MEETING FEES |
|
|
|
|
|
|
Regular Monthly |
Other |
|
Donner Summit PUD* |
President |
$ 300 |
$100 |
|
|
Vice Pres. |
260 |
100 |
|
|
Directors (3) |
225 |
100 |
|
|
*Paid even if excused |
|
|
|
|
|
|
|
|
T-TSA |
|
$100 |
$100 |
|
|
|
|
|
|
Tahoe Donner PUD |
|
$400 per month + Medical Plan |
|
|
BOARD EXPENSE |
|
Donner Summit |
T-TSA |
|
|
|
|
|
|
|
’05-06 |
$10,100 |
NA |
|
|
’06-07 |
12,740* |
$ 6,700 |
|
|
’07-08 (budget) |
16,820 |
12,000 |
4/13/2008